The construction and completion of mainline and other associated works for Package CA3 starts from CH. 4200 to CH. 7800 which make the total length of approximately 5.2 km in total. The construction of Package CA3 involves mainly elevated expressway mainline structure and minor at-grade construction. The package also involves the construction of Alam Damai Interchange with five (5) ramps – MA10, MA20, MA11, MA21 and MA30 and slip road Alam Damai.

Site Progress

May 2022

Feb 2022

January 2022

December 2021

October 2021

September 2021

August 2021

July 2021

June 2021

April 2021

March 2021

February 2021

January 2021

December 2020

November 2020

October 2020

.